Total Projects
—
Across 8 categories
In Progress
—
Currently executing
Completed
—
On schedule
Upcoming
—
Planned / Not Started
Est. Total Budget
$94.2M
Across all scopes
CO Exposure
$1.45M
12 change orders
Avg Completion
—
Active projects only
Project Horizon
24mo
Jan 2026 – Dec 2027
Category Breakdown
Key Milestones
Risk Register
Critical
Gen #5 rigging — crane access window coordination with LA DOT
Critical
Rooftop structural load — cooling addition pending PE sign-off
High
ACM scope creep — FL 8-12 showing 40% more asbestos than survey
High
HV switchgear lead time — 28-week delivery impacts parallel tasks
High
Floor load rating — FL 18-22 may need additional steel reinforcement
Medium
SCAQMD permit timeline — fuel day tank expansion pending
Medium
Live DC operations during vertical conduit installation
Medium
BMS/DCIM integration — multi-vendor legacy systems 15+ floors
Project / Task
Start
Finish
Floor
Done
12
Total COs
5
Approved
4
Pending
3
Under Review
$1,451,000
Total Exposure
| CO # | Category | Project / Scope | Description | Submitted By | Date | Amount | Days Open | Status |
|---|